Greenspan Electric
Renewable Energy Investment

Balquhindachy
-
July '07 - Commissioned our first wind turbine in Aberdeenshire
-
January '09 - Installed two more turbines at the same site
-
All three turbines are Vestas V52-850kW with a tip height of 75m
-
Each turbine produces enough renewable electricity to power over 600 homes
Cairnmore
-
May '10 - Commissioned three wind turbines near Rhynie, Aberdeenshire
-
All three turbines are Vestas V52-850kW with an 81m tip height
-
February '11 - Planning application submitted for a five turbine extension
St. Fergus Moss
-
March '11 - Planning permission for three 100m wind turbines secured
-
Engineering, Procurement and Construction in motion
Other Developments
-
October '09 - As part of a joint venture we commissioned an Enercon E48-800kW wind turbine in Aberdeenshire
-
We are currently exploring potential joint ventures with other parties to develop and invest in renewable energy developments